Home > Articles > Queen's football > New stadium project is on schedule

New stadium project is on schedule


Posted: August 27th, 2015 @ 6:29pm


Work continues on site services for the new Richardson Stadium
Work continues on site services for the new Richardson Stadium
By CLAUDE SCILLEY

Fans at Sunday’s football game at Richardson Stadium won’t be able to see any of the work that’s been done for the new facility these past six weeks.

But they will be able to park on it.

All people at the Ontario University Athletics season opener will see of the early work for the new stadium will be a pristine parking surface east of the current structure, some footings for the parking lot lights, and some excavation work underway at the southeast corner of the stadium.

Underneath, all of the site services—sanitary and storm sewers, water works, electricity and communications infrastructure—have been put in place, ready to be connected to Richardson III, which is scheduled to be completed in time for the opening of the 2016 football season.

“We’re not going to be able to complete all of the site work but we’re going to get a very good portion of it done,” Greg Sullivan, vice-president and general manager of M. Sullivan and Son said. “It’s not sexy work, it’s all buried, but it’s all very important civil infrastructure.”

Work began July 13 on the new Richardson Stadium. Site services have been installed to the east of the current structure, as seen from this photo taken from atop John Orr Tower. —John Garrah/M.Sullivan and Son
Work began July 13 on the new Richardson Stadium. Site services have been installed to the east of the current structure, as seen from this photo taken from atop John Orr Tower. —John Garrah/M.Sullivan and Son
Given that the Gaels realistically had no place to relocate for this year, when the final go-ahead was given for the project the decision was made to leave the team in the old place for another year, and get to work on the new stadium immediately at the end of the 2015 season.

It was an imposing timeline—10 months to demolish the old structure and build anew, with three of those months a Canadian winter—but the university gave the contractor permission to do what it could as soon as the requisite municipal permits were in hand.

Workers were on the site July 13.

“It was doable if the weather co-operated,” site supervisor and project manager John Garrah said, “but the university agreeing to let us come in early was probably the biggest helper, because it gives us some breathing room.”

Though approval to build the new stadium wasn’t granted by the Queen’s Senate until last December, in anticipation of its inevitability Sullivan has been working on the project for three years.

“We’ve worked hard and now it’s game day,” Garrah said. “We’ve got to get it done.”

Garrah, who grew up in Portsmouth, in the shadow of the stadium—“I used to be one of the kids who cut the fence to get into the games”—said work will continue south of the field, into the south parking lot, to complete the north-south tie-ins for all the services.

It will be close to normal for fans attending Sunday's football game. —John Garrah/M.Sullivan and Son
It will be close to normal for fans attending Sunday's football game. —John Garrah/M.Sullivan and Son
There won’t be any changes for the team or fans, though for Sunday’s game only the two east gates—to the student bleachers—won’t be open. However, with the tennis courts gone, the parking lot will now hold more than 200 cars.

“It’s close to being normal but not quite,” Garrah said. “You don’t ant to inconvenience anyone. They’re still living here.

“It’s going to be a little inconvenience for this year; it’s going to be a huge benefit for the 2016 season.”

The parking lot is scheduled to be paved, Garrah said, but that work is being held in abeyance as a buffer against future unforeseen expenses.

Tenders are open for the next two phases of the project: the 400-plus micro-piles that will, essentially, hold up the place, and construction of the grandstand. There are two grassy knolls on the east side of the field and nothing to the south of it, where the scoreboard will be, and Garrah hopes to get some work done in those areas before the snow flies.

“I would like to have (the scoreboard foundation) done, as well as some micropiles for the grandstand where there is nothing now,” Garrah said. “If we can get a head start on this foundation, at least, and get it in the ground before freezing, that helps us huge with the end schedule.”

There are about 20 workers on site now, he said, in a crew that will number about 50 when the football season ends. “That’s when this project is really going to ramp up.”

Sullivan said the co-operation among his company, the university, the city and sub trades is one reason the project is proceeding as well as it is.

“People have realized that this is good for the community,” he said. “Everyone’s been super co-operative. That doesn’t always happen.

“Even Mother Nature’s been looking after us. We’ve had great weather the last four weeks.”

One unique aspect of this project—among the company’s recent work are the new police station and the new medical building at Queen’s—is that virtually all of it is outdoors. Other than the east building, which will house washrooms, concessions and ticketing, there’s little opportunity to finish a building’s shell so work can proceed indoors during inclement weather.

“We’ve researched it, we put our legwork in. Now we’ve just got to do it,” Sullivan said.

“We are extremely concerned inside this office with schedule, but pressure makes diamonds and we’re going to do what we can. We’ve been in business for 101 years by not failing, so we’re certainly going to give it our best hook.

“It’s a very important job for M. Sullivan and Son, as well as the university, as well as the community. If anyone deserves a new facility, it’s the Queen’s Golden Gaels.”


Related Articles:


Support sportkingston

Thank You To All Our Generous Supporters!
We Need Your Help Too!
Help Support This Site
Follow sportkingston

Follow Us On Twitter
Follow Us On Twitter
Recent Stories


He coached young men, not just football players
All done
Queen's athletes win major volleyball awards
To buy or not to buy
QE splits two games at EOSSAA single-A basketball
KC downs Frontenac in EOSSAA basketball final
Weekend defeats send Gaels to preliminary playoff round
Queen's to host men's basketball playoff Wednesday
High school volleyball matches tonight at Regi
EOSSAA will try again to play basketball Tuesday
Categories


Amateur Sport

Baseball

Basketball

CIS Football

Cross Country

Fastball

Field hockey

Football

Frontenacs 50th

Grenadiers Football

High School Sports

Hockey

Intercollegiate Sport

Junior Hockey

Kingston Kings

Lacrosse

Napanee Express

Opinion

Pan Am Games

Queen's football

RMC Looking Back

Rowing

Rugby

Sailing

Soccer

Today In Jr. Hockey Playoff History

Track and field

Uncategorized

Volleyball
Search

Looking for a specific article, person, event, or subject?





Management Login

Powered By FlexCMS
Powered By FlexCMS